0

ITCertMaster can not only save you valuable time, but also make you feel at ease to participate in the exam and pass it successfully. ITCertMaster has good reliability and a high reputation in the IT professionals. You can free download the part of GIAC GCPM exam questions and answers ITCertMaster provide as an attempt to determine the reliability of our products. I believe you will be very satisfied of our products. I have confidence in our ITCertMaster products that soon ITCertMaster's exam questions and answers about GIAC GCPM will be your choice and you will pass GIAC certification GCPM exam successfully. It is wise to choose our ITCertMaster and ITCertMaster will prove to be the most satisfied product you want.

In order to meet the demand of most of the IT employees, ITCertMaster's IT experts team use their experience and knowledge to study the past few years GIAC certification GCPM exam questions. Finally, ITCertMaster's latest GIAC GCPM simulation test, exercise questions and answers have come out. Our GIAC GCPM simulation test questions have 95% similarity answers with real exam questions and answers, which can help you 100% pass the exam. If you do not pass the exam, ITCertMaster will full refund to you. You can also free online download the part of ITCertMaster's GIAC certification GCPM exam practice questions and answers as a try. After your understanding of our reliability, I believe you will quickly add ITCertMaster's products to your cart. ITCertMaster will achieve your dream.

Fantasy can make people to come up with many good ideas, but it can not do anything. So when you thinking how to pass the GIAC GCPM exam, It's better open your computer, and click the website of ITCertMaster, then you will see the things you want. ITCertMaster's products have favorable prices, and have quality assurance, but also to ensure you to 100% pass the exam.

ITCertMaster is a website specifically provide the certification exam information sources for IT professionals. Through many reflects from people who have purchase ITCertMaster's products, ITCertMaster is proved to be the best website to provide the source of information about certification exam. The product of ITCertMaster is a very reliable training tool for you. The answers of the exam exercises provided by ITCertMaster is very accurate. Our ITCertMaster's senior experts are continuing to enhance the quality of our training materials.

ITCertMaster's GIAC certification GCPM exam testing exercises is very similar with real exam questions. If you choose ITCertMaster's testing practice questions and answers, we will provide you with a year of free online update service. ITCertMaster can 100% guarantee you to pass the exam, if you fail to pass the exam, we will full refund to you.

Exam Code: GCPM
Exam Name: GIAC (GIAC Certified Project Manager Certification Practice Test)
Guaranteed success with practice guides, No help, Full refund!
397 Questions and Answers
Updated: 2013-11-05

ITCertMaster is a professional IT certification sites, the certification success rate is 100%. This number is proved by candidates through practice. Because ITCertMaster has a strong IT team of experts, they are committed to study exam questions and answers, and serve the vital interests of the majority of candidates. They use their own professional mind and experience to meet the needs of the candidates. According to the needs of the candidate, they consider the issue from all angles, and manufacturing applicability exam training materials. This material is GIAC GCPM exam training materials, which including questions and answers.

Our latest training material about GIAC certification GCPM exam is developed by ITCertMaster's professional team's constantly study the outline. It can help a lot of people achieve their dream. In today's competitive IT profession, if you want to stabilize your own position, you will have to prove your professional knowledge and technology level. GIAC certification GCPM exam is a very good test to prove your ability. If you have a GIAC GCPM certification, your work will have a lot of change that wages and work position will increase quickly.

GCPM Free Demo Download: http://www.itcertmaster.com/GCPM.html

NO.1 You are in a project to create a Website. Your project team has met a few times and you're working
with them to develop the project's WBS. Jan, a marketing expert, is in disagreement with Larry over how
the Website should function. Gary and Gina are in disagreement over who'll take the lead on the design of
the software for the Website. Mark, Mary, and Martha are all bickering about the photo management
approach for the Website's pictures. What stage of team development is your project team currently in?
A. Forming
B. Storming
C. Performing
D. Norming
Answer: B

GIAC exam   GCPM   GCPM exam simulations   GCPM test

NO.2 Which of the following is described in the statement below.?
"It is a group of sequential and related project phases that are defined by the organization and control
needs of the management or organizations concerned with the project, the nature of the project itself, and
the application area."
A. Verify scope
B. Project charter
C. Activity list
D. Project life cycle
Answer: D

GIAC test   GCPM braindump   GCPM

NO.3 You work as a project manager for Xxxx Inc. You are in the project kickoff meeting. Which of the
following documents are reviewed during the project kickoff meeting?
Each correct answer represents a complete solution. Choose all that apply.
A. Project budget
B. Project WBS
C. Project charter
D. Project scope
Answer: A,C,D

GIAC   GCPM demo   GCPM pdf   GCPM test answers

NO.4 You are a Project Manager in your organization who is managing a considerably huge budget project
to develop new software. Considering the varied nature of your stakeholder group, you would like to put
together a plan as to what information the stakeholders need, and how to provide that information. What
is the document that you would need, and as part of which process group would you achieve this?
A. Communications Management Plan, Execution Process group
B. Project Management Plan, Planning Process Group
C. Communications Management Plan, Planning Process Group
D. Project Management Plan, Initiating Process Group
Answer: C

GIAC   GCPM   GCPM   GCPM exam   GCPM exam prep   GCPM pdf

NO.5 You work as a project manager for Xxxx Inc. A new project has been proposed to change all keyboards
of every computer in your organization. There are 1,600 keyboards that will need to be removed and
replaced with wireless keyboards. What document will you first need to start this project?
A. Project risk statement
B. Risk register
C. Project charter
D. Contract for new keyboards
Answer: C

GIAC   GCPM   GCPM

NO.6 Which of the following components of EVA is described in the statement below?
"It is a measure of how much of the project value has been earned so far through completed work, that is,
the budgeted cost of the work that has been performed through the project status date."
A. PV
B. AC
C. SV
D. EV
Answer: D

GIAC   GCPM questions   GCPM   GCPM practice test   GCPM test questions

NO.7 You are a new Project Manager that has been entrusted with a software development project that is in
progress. A sub-contracting company has been awarded a cost reimbursable contract to do the
development work on this project, and the project has been completed. While trying to close this
procurement, you discover that still there are some unresolved claims. However, the sub contract
company does not accept that these claims are unresolved. Which of the following is the best method for
reaching the final equitable settlement?
A. Litigation
B. Mediation
C. Direct negotiation
D. Alternative dispute resolution
Answer: C

GIAC answers real questions   GCPM dumps   GCPM dumps   GCPM   GCPM

NO.8 You work as a project manager for Xxxx Inc. Which of the following processes will you use to formalize
the acceptance of the completed project deliverables?
A. Verify scope
B. Report performance
C. Expert judgment
D. Perform quality control
Answer: A

GIAC exam simulations   GCPM practice test   GCPM certification training   GCPM exam   GCPM answers real questions

NO.9 You are the project manager for your organization. Marcy, a project stakeholder, is demanding that you
add some deliverables to your project scope for free. You explain to Marcy that it's too late in the project
execution to consider adding these deliverables, as most of the software your project team is creating is
nearly done. Marcy and you escalate the issue to management.
Management decides that you will add the deliverables to the project scope if Marcy pays a significant fee
and allows you additional time to complete the project. What conflict resolution method has management
offered?
A. Issue management
B. Compromising
C. Forcing
D. Confronting
Answer: B

GIAC   GCPM   GCPM   GCPM   GCPM

NO.10 Which of the following processes describes the statement below?
"It consists of the processes required to ensure that the project contains all the work required to complete
the project effectively."
A. Project communications management
B. Project scope management
C. Risk management
D. Project human resource management
Answer: B

GIAC original questions   GCPM demo   GCPM test questions   GCPM

NO.11 Which of the following is described in the statement below?
"It is a tool that defines a project and groups the project's discrete work elements in a way that helps
organize and define the total work scope of the project."
A. WBS
B. RBS
C. Gantt chart
D. Critical path
Answer: A

GIAC test answers   GCPM exam   GCPM   GCPM test questions

NO.12 You work as a project manager for Xxxx Inc. You have to subdivide project
deliverables and project work into smaller, more manageable components. Which of the following
processes will you use to perform the above task?
A. Create WBS
B. Verify scope
C. Control scope
D. Define activities
Answer: A

GIAC   GCPM questions   GCPM answers real questions   GCPM practice test   GCPM

NO.13 You work as a project manager for Xxxx Inc. You are working on a project that has a budget of
$805,000 and you have completed 45 percent of the project work. Due to some errors, however, you have
actually spent $430,000 of the budget. Management wants to know the project's cost performance index.
Which of the following values will you report?
A. 0.87
B. 0.80
C. 0.84
D. 0.86
Answer: C

GIAC demo   GCPM study guide   GCPM certification training   GCPM original questions

NO.14 Which of the following are the characteristics of the project life cycle?
Each correct answer represents a complete solution. Choose all that apply.
A. Cost and staffing are low at the start, are high as the work is carried out, and decrease as the project
comes towards the end.
B. Stakeholders influences, risk, and uncertainty are at peak in the beginning of the project.
C. Skills to influence the final characteristics of the project's product, without much impact on cost, is at
peak in the beginning of the project and reduces as the project progresses towards completion.
D. It is limited by constraints, including resource constraints.
Answer: A,B,C

GIAC   GCPM test   GCPM   GCPM   GCPM original questions

NO.15 You work as a project manager for Xxxx Inc. You are working on several projects. Your projects vary in
size and budget. You have to calculate the ratios of schedule and cost compared to plan, so that you can
compare relative schedule and cost performance of each project. Which of the following components of
EVM provide measures of schedule and cost performance that are not affected by the size of the project?
A. BAC and EAC
B. CPI and SPI
C. CV and SV
D. PV and EV
Answer: B

GIAC test   GCPM   GCPM   GCPM

NO.16 You are the project manager of the NHT Project. This project has 12,345 office doors to install
throughout a campus. Each of the doors costs the project $456 and requires special hardware to
electronically lock and open the doors. You've gathered the project team before they begin the installation
for a hands-on training. As a group you and the project team install 50 doors following a checklist of
instructions so that every door will be installed exactly the same throughout the campus and with minimal
waste. This is an example of what project execution technique?
A. Preventive action
B. Implemented corrective action
C. Quality control
D. Defect repair validation
Answer: A

GIAC   GCPM   GCPM   GCPM test questions

NO.17 You are the program manager for your project. You are working with the project managers regarding
the procurement processes for their projects. You have ruled out one particular contract type because it is
considered too risky for the program. Which one of the following contract types is usually considered to be
the most dangerous for the buyer?
A. Cost plus incentive fee
B. Time and materials
C. Cost plus percentage of costs
D. Fixed fee
Answer: C

GIAC braindump   GCPM   GCPM practice test

NO.18 Which of the following processes formally permits the initiation of a project and marks the kickoff for all
consequent development activities to begin?
A. Develop project charter
B. Develop project management plan
C. Develop project scope statement
D. Develop project team
Answer: A

GIAC dumps   GCPM   GCPM test answers   GCPM exam simulations   GCPM   GCPM

NO.19 You work as a project manager for Xxxx Inc. You are performing a task to generate a hierarchical list of
resources related by function and resource type that is used to facilitate planning and controlling of project
work. Which of the following components of project management will you use to accomplish the above
task?
A. PERT chart
B. RBS
C. Gantt chart
D. WBS
Answer: B

GIAC exam prep   GCPM   GCPM   GCPM answers real questions

NO.20 Which of the following techniques is described in the statement below?
"It evaluates the abstract early start and finish dates and late start and finish dates for all activities devoid
of any resource limitations by performing a forward and backward pass analysis through the schedule
network."
A. Resource utilization
B. Critical path method
C. Critical Chain method
D. Resource leveling heuristic
Answer: B

GIAC   GCPM   GCPM   GCPM exam

NO.21 You work as a project manager for Xxxx Inc. Which of the following stages of the process group, if not
performed well by you, is unlikely that the project will be successful in meeting the business needs?
A. Monitoring and controlling
B. Initiation
C. Executing
D. Planning and design
Answer: B

GIAC   GCPM certification   GCPM

NO.22 Which of the following processes formally permits the initiation of a project and marks the kickoff for all
consequent development activities to begin?
A. Develop project scope statement
B. Develop project management plan
C. Develop project charter
D. Develop project team
Answer: C

GIAC   GCPM questions   GCPM

NO.23 You work as a project manager for Xxxx Inc. You are performing steps to carry out and finish the
project according to the measures drawn through the planning stage. Which of the following stages of the
project are you working on?
A. Monitoring and controlling
B. Closing
C. Initiation
D. Execution
Answer: D

GIAC   GCPM   GCPM study guide

NO.24 Diane is the project manager of the HGF Project. A risk that has been identified and analyzed in the
project planning processes is now coming into fruition. What individual should respond to the risk with the
preplanned risk response?
A. Diane
B. Risk owner
C. Subject matter expert
D. Project sponsor
Answer: B

GIAC   GCPM practice test   GCPM exam dumps   GCPM

NO.25 You are using the PDCA model to determine, implement, monitor, control, and maintain Information
Security Management System or ISMS. You have to evaluate the new processes and match up to the
results against the probable results to determine the differences. In which of the following phases of the
PDCA are you working?
A. Do
B. Act
C. Plan
D. Check
Answer: D

GIAC   GCPM dumps   GCPM   GCPM

NO.26 James works as the project manager for a software project. He and his team are on the Direct and
Manage Project Execution process. All of the following are inputs of this process except for which one?
A. Project charter
B. Organizational process assets
C. Enterprise environmental factors
D. Approved environmental requests
E. Project management plan
Answer: A

GIAC   GCPM   GCPM   GCPM dumps

NO.27 You work as a project manager for Xxxx Inc. You report the project details directly to the vice president
and the administrator of your organization. In which of the following types of organization structures are
you working?
A. Functional
B. Matrix
C. Jury
D. Projectized
Answer: B

GIAC dumps   GCPM exam simulations   GCPM

NO.28 Charlie has just completed the project according to the terms of the contract. She and the customer
are completing a walk through of the project deliverables, and the customer is asking for changes to the
deliverables before she'll accept the product. What project management process should manage the
documented change request that may come from scope verification?
A. Scope management
B. Perform integrated change control
C. Control Scope
D. Control change control
Answer: B

GIAC original questions   GCPM study guide   GCPM test answers

NO.29 You work as a project manager for BlueWell Inc. Which of the following techniques will you use to
determine whether particular work can best be accomplished by the project team or must be purchased
from the outside sources?
A. Expert Judgment
B. Make-or-Buy Analysis
C. Contract Types
D. Procurement Negotiations
Answer: B

GIAC practice test   GCPM   GCPM test questions

NO.30 Which of the following are the characteristics of a project?
Each correct answer represents a complete solution. Choose all that apply.
A. Its success is measured by evaluating whether it meets or exceeds expectations of the stakeholders.
B. It is temporary in nature and has a definite beginning and ending date.
C. It is completed when the project goals are achieved.
D. It is common in nature.
Answer: A,B,C

GIAC   GCPM   GCPM   GCPM braindump   GCPM answers real questions

ITCertMaster offer the latest 000-318 Practice Test and high-quality HP2-B101 PDF Exam Questions training material. Our JN0-730 VCE testing engine and 000-273 dumps can help you pass the real exam. High-quality HP0-S33 Exam Questions & Answers can 100% guarantee you pass the exam faster and easier. Pass the exam to obtain certification is so simple.

Article Link: http://www.itcertmaster.com/GCPM.html

Post a Comment

 
Top